9 Glenesk Road, Piha
(35 Meters Timber Retaining wall)
We are delighted to announce the successful completion of a significant project in collaboration with Auckland Transport and Downer NZ. Situated at 9 Glenesk Road, Piha, our team undertook the construction of a 35-meter-long timber retaining wall along the picturesque Piha River.
Client: Auckland Transport
Main Contractor: Downer NZ
Project Type: Timber Retaining wall
Location: Glenesk Road, Piha
Key project highlights include:
- Excavation and rock drilling ranging from 8 meters deep
- Installation of 9-meter-long piles, with drilling depths reaching approximately 8 meters
- Drill hole 600 diameter and 23 post installed
- Installation timber lagging 35 meter long
- Initial clearance of a 20-meter slip along the river bank
- Completion of 120 square meters of road works and sealing at the site
- Implementation of 400 square meters of slip stabilization, featuring erosion matting and hydro seeding
- Installation of safety railings upon project completion
Throughout the project lifecycle, our team ensured meticulous attention to detail and adherence to environmental best practices. We are proud to report that the project was delivered to Auckland Transport's satisfaction, meeting all specified requirements without encountering any challenges.